Battlefield Parkway


OWNER:

Virginia Department of Transportation (VDOT)

DESIGNER:

Dewberry Consultants Inc.

CDESLIVERY METHOD:

Design-Build

COMPLETION DATE:

November 2009

 

Shirley Contracting Company, LLC with Dewberry Consultants LLC as the Lead Designer was
selected by the Virginia Department of Transportation (VDOT) in May 2007 to design and
construct 0.7 miles of Battlefield Parkway, a four lane roadway from Kincaid Boulevard to Route
7. The Project included dual 1,250-foot bridges spanning the Washington and Old Dominion
(W&OD) trail and the Tuscarora Creek floodplain. Additionally, it included a 260-foot extension of
a triple barrel box culvert, mechanically stabilized earth walls, two signals, roadway lighting,
and a structure mounted sound barrier. The Design-Build Team’s responsibilities included all
design and engineering, permitting, right-of-way acquisition, utility relocations, construction,
and quality assurance and quality control. The project required close coordination with the
Northern Virginia Regional Park Authority (NVRPA) to reduce the impacts to the W&OD Trail.

The Team coordinated closely with the Town of Leesburg and adjacent property owners
during the design phase to minimize future costs for completing future road improvements
proposed within the project limits. At no cost to VDOT, ther Team prepared exhibits of the future
Route 7 and Battlefield Parkway interchange for review by the Town and VDOT and set the
profile elevation on our project at an agreed upon elevation to reduce rework during future
interchange construction. The Team also coordinated with VDOT and the Town to include a
“T” intersection and stub-out to the future alignment of Russell Branch Parkway. The Team
delayed construction in this area until funding for these improvements could be approved
through the Town of Leesburg and the scope added to our contract. We then resequenced the
schedule so these additional improvements could be completed without delay to the original
completion date.

The Shirley Design-Build Team implemented an aggressive project schedule resulting in early
plan approval. This approval facilitated obtaining not only the required environmental permits
early, but also allowed early right-of-way acquisition through right-of-entry agreements with
adjacent landowners, which allowed construction to begin three months ahead of schedule.
Ultimately, the project was delivered three months ahead of schedule.